Key Points
- Canton City Council is considering changes to data centre zoning rules approved in July.
- The proposed amendments address screening, backup-generator schedules and decommissioning requirements.
- An earthen berm could be waived where existing landforms provide sufficient screening.
- Generator provisions would require compliance with state and local air-pollution rules and permits.
- A public hearing is scheduled for November 30.
Inverted-pyramid reporting
- Key Points
- What changes is Canton considering for data centres?
- What did Canton approve in July?
- When will the public hear the proposed changes?
- What could the changes mean for Canton’s data-centre rules?
- Background: Why did Canton adopt specific data-centre rules?
- How could the amendments affect Canton’s planning process?
uk/local/cardiff/canton/">Canton (The Wales Times) November 26, 2026 — Canton City Council is considering amendments to data centre zoning regulations adopted in July, with proposed changes covering site screening, backup-generator operations and the removal of facilities after closure. The council is scheduled to hold a public hearing on November 30. The review follows concerns and continued examination of rules governing setbacks, noise, utility lines, generators and other data-centre features.
What changes is Canton considering for data centres?
As reported by The Canton Repository on November 26, the proposed amendments would revise several provisions in the July zoning ordinance. The changes include rules for screening, generator schedules and decommissioning.
The July ordinance required an earthen berm around a site perimeter as a property barrier. Under the proposed amendment, that requirement could be waived if existing landforms are judged to provide sufficient screening.
The proposal would also revise requirements for backup generators. Generators would have to comply with state and local air-pollution regulations and applicable permitting requirements.
What did Canton approve in July?
Canton City Council approved the data-centre zoning ordinance by an 8–3 vote in July. The measure amended the planning and zoning code by adding a dedicated data-centre section and revising definitions.
The rules established requirements involving setbacks, buffers, noise, utility lines and generators. Council members also agreed to continue examining the regulations after adoption.
Available meeting records identify the ordinance as Ordinance 30, passed on July 27, 2026. The recorded no votes included Chris Smith, Richard Sacco and Frank Morris in one meeting summary, while another meeting account lists Frank Morris, John Kimbrough and James Cole among the dissenting votes; the differing records have not been reconciled in the available material.
When will the public hear the proposed changes?
The council’s public hearing on the proposed amendments is scheduled for November 30. Any final changes would follow the council’s consideration of public testimony and the proposed ordinance.
What could the changes mean for Canton’s data-centre rules?
If approved, the amendments would give Canton greater flexibility over perimeter screening where natural landforms already limit visibility. They would also clarify that backup generators remain subject to air-quality controls and permitting requirements, while the decommissioning provisions could establish clearer expectations for facilities that cease operating.
The changes would not replace the July framework; they would modify selected requirements while the city continues reviewing how data centres should be regulated.
Background: Why did Canton adopt specific data-centre rules?
Canton created a dedicated zoning framework in July as data-centre development raised questions about land use, noise, infrastructure and environmental controls. The ordinance introduced standards for setbacks, screening, utility lines and backup generators. Council approved the measure 8–3 while agreeing that the regulations should continue to be examined. The proposed amendments represent the next stage of that review before the scheduled public hearing.
How could the amendments affect Canton’s planning process?
The proposed changes could make the rules easier to apply to sites with existing natural barriers while preserving regulatory oversight of generators and facility closure. Developers could face a more site-specific screening assessment instead of an automatic berm requirement. Residents and council members would retain an opportunity to comment at the November 30 hearing. The final effect will depend on the wording adopted after public testimony and council consideration.